Pengurasan Saluran Air di Jalan Kesehatan Capai 70 Persen

Channel Dredging on Jalan Kesehatan Has Reached 70 Percent

The channel dredging work through 49 workers that has been carried out since February on Jalan Kesehatan I to X, RW 06 Petojo Selatan Urban Village, Gambir, Central Jakarta has reached 70 percent.

If it is ignored, it will trigger inundation

Gambir Sub-district Water Resources (SDA) Unit Head Muhammad Imawan mentioned that the channel was dredged to follow up on residents' requests through Musrenbang 2021 since mud thickness had reached 70 centimeters.

"If it is ignored, it will trigger inundation," he conveyed, Tuesday (3/29).

Five Sacks of Mud and Garbage Collected from Drain on Kelapa Island

According to him, the channel from Jalan Kesehatan I to X has a length of 10,000 meters with an average width of 80 centimeters and a height of one meter.

"We have finished the dredging in the channel along Jalan Kesehatan I to V. While from Jalan Kesehatan IV to X is estimated to be completed in mid-April," he said.

It was done manually using simple tools such as a hoe, crowbar, cart, and plastic sack.

"So far, we have transported about 50 cubic meters of mud," he stated.

Linked News
Popular News indeks
  1. Transjakarta Adjusts Routes Amid Demonstrations

    access_time28-10-2026 remove_red_eye564 personAldi Geri Lumban Tobing
  2. Central Jakarta Helps 879 Residents Retrieve Withheld Diplomas

    access_time30-10-2026 remove_red_eye535 personFolmer
  3. Tourism Industry Workforce Capacity Continues to Be Improved

    access_time30-10-2026 remove_red_eye533 personAldi Geri Lumban Tobing
  4. Free Health Checks and TB Screening Held at RPTRA Tamplas Bambu

    access_time30-10-2026 remove_red_eye531 personNurito
  5. Jakarta to Host World Cities Culture Summit 2027

    access_time31-10-2026 remove_red_eye531 personBudhi Firmansyah Surapati